When an OFO is required, the Pacific Gas and Electric Company's California Gas Transmission Operations Department establishes an OFO tolerance band. CGT establishes the OFO tolerance band based primarily upon how much additional (or less, in the low inventory case) inventory the pipeline can absorb while remaining within acceptable operating limits. Customers are then obligated to provide daily supply within the stated tolerance band percentage of usage or face noncompliance charges.
Section D.2.c of the OFO Settlement describes the relationship between OFO stages, tolerance bands, and noncompliance charges. Stage 5 OFOs were added with California Public Utilities Commission Decision 03-12-061. Stages 3.1, 3.2 and 3.3 OFOs were added with California Public Utilities Commission Decision 22-04-042 and detailed in PG&E Advice 4617-G. The tolerance band may range from 0% to 25%, as follows:
Stage | Tolerance Band as % of Usage | Noncompliance Charge $/Dth |
---|---|---|
Stage 1 | up to +/-25% | $0.25 |
Stage 2 | up to +/-20% | $1.00 |
Stage 3 | up to +/-15% | $5.00 |
Stage 3.1 | up to +/-15% | $10.00 |
Stage 3.2 | up to +/-15% | $15.00 |
Stage 3.3 | up to +/-15% | $20.00 |
Stage 4 | up to +/-5% | $25.00 |
Stage 5 | up to +/-5% | $25.00 + Daily Citygate Index* |
CGT considers a number of factors when setting a noncompliance charge including; real-time market pricing data, response to recently called OFOs and the potential impact of an OFO's failure to maintain inventories within acceptable operating limits. CGT's goal is to set the charge at a level that is sufficient to give customers incentive to balance their loads without being onerous.
*The Daily Citygate Index is defined as the daily PG&E Citygate Index Price as published in Gas Daily for the day of the OFO, rounded up to the next whole dollar.
Back to Introduction to Operational Flow Orders (OFO) Index.
Related Pages
12. Pipeline Inventory
To maintain a safe and reliable pipeline system, Pacific Gas and Electric Company's pipeline inventory must operate within ...
13. Storage Assets Available for Balancing and Market Center
A portion of Pacific Gas and Electric Company's storage assets is set aside for use in balancing the pipeline system ...
14. Supply and Demand Forecast and OFO
The pipeline inventory forecast in Pipe Ranger sometimes changes quite abruptly. This can make ...