As of Thursday, June 27, 2024
Redwood Path Maintenance
Capacity in MMcf/d | ||
---|---|---|
Dates | Redwood Path | Maintenance Notes |
June 27 - 30 |
2110 |
Indian Springs Station Maintenance |
July 01 - 10 |
2090 |
Indian Springs Station Maintenance |
July 11 |
2010 |
Tionesta Station Maintenance |
July 12 - 13 |
2090 |
Indian Springs Station Maintenance |
July 14 |
2040 |
Indian Springs Station Maintenance |
July 15 - 18 |
1890 |
Burney Station Maintenance |
July 19 |
1990 |
Burney Station Maintenance |
July 20 - 21 |
2090 |
Indian Springs Station Maintenance |
July 22 |
2080 |
Delevan Station Maintenance |
July 23 - 24 |
2050 |
Delevan Station Maintenance Gerber Station Maintenance |
July 25 - 31 |
2090 |
Indian Springs Station Maintenance |
June Max Capacity: 2180 | ||
July Max Capacity: 2170 |
Baja Path Maintenance
Capacity in MMcf/d | ||||
---|---|---|---|---|
Dates | Kettleman | Hinkley | Topock | Maintenance Notes |
June 17 - 28 |
500 |
540 |
975 |
Hinkley Station Maintenance L300B Pipeline Maintenance L300A Pipeline Maintenance |
June 29 - 30 |
500 |
600 |
975 |
Hinkley Station Maintenance L300B Pipeline Maintenance |
July 01 - 07 |
500 |
600 |
975 |
L300A Pipeline Maintenance |
July 08 - 26 |
380 |
600 |
975 |
L300A Pipeline Maintenance Kettleman Station Maintenance |
July 27 - 31 |
500 |
975 |
975 |
L300A Pipeline Maintenance |
June Max Capacity: 975 | ||||
July Max Capacity: 975 |
Limitations at Specific Interconnect Points
Redwood Path
Dates | Capacity | Maintenance Notes |
---|
Capacity information is in MMcf/d
Baja Path
Dates | Capacity | Maintenance Notes |
---|---|---|
June 01 - 30 |
713 |
El Paso Interconnect at Topock limited for maintenance |
July 01 - 31 |
713 |
El Paso Interconnect at Topock limited for maintenance |
Capacity information is in MMcf/d
Storage Maintenance
Injection
Dates | Capacity | Maintenance Notes |
---|
Capacity information is in MMcf/d
Withdrawal
Dates | Capacity | Maintenance Notes |
---|
Capacity information is in MMcf/d
Pipeline Maintenance History Download
Maintenance will not appear in the archive until after it's been removed from the Operating Data | Pipeline Maintenance page above. You can download Redwood and Baja pipeline maintenance information as far back as November 1, 2016. You can download Limitations at Specific Interconnect Point information as far back as March 21, 2018. You can download Storage Maintenance information as far back as December 11, 2020.
Prospective Maintenance Document
Last revised: June 18, 2024
Download our Prospective Maintenance document for a 6-12 month outlook of proposed maintenance on the CGT pipeline system. Note that this document is revised monthly and is offered in addition to our existing month-out Pipeline Maintenance information listed above.
Report any accessibility barriers you encounter when using our site by contacting CGTPipeRanger@pge.com. The mailbox is monitored during our business hours (M-F; 6am-3pm PT). We will respond within 3 business days.