Pipeline Maintenance

As of Thursday, March 27, 2025

Redwood Path Maintenance

Capacity in MMcf/d
Dates Redwood Path Maintenance Notes

March 25 - 27

1570

Delevan Station Maintenance

April 01 - 09

1846

L-401 Pipeline Maintenance


Note: If ISPs (WG and CGVS) are on overall net injection, the Redwood Path capacity may increase up to 1900 MMcf/d

April 10

2010

Burney Station Maintenance

April 11

2140

Burney Station Maintenance

April 13

2210

Delevan Station Maintenance

April 14

2160

Delevan Station Maintenance

April 15

2150

Delevan Station Maintenance

Gerber Station Maintenance

April 16

2050

Gerber Station Maintenance

April 17

2160

Gerber Station Maintenance

April 24 - 28

1858

L-400-3 Pipeline Maintenance

 

Note: If ISPs (WG and CGVS) are on overall net injection, the Redwood Path capacity may increase up to 1990 MMcf/d

April 29

1840

L-400-3 Pipeline Maintenance

Tionesta Station Maintenance

 

Note: If ISPs (WG and CGVS) are on overall net injection, the Redwood Path capacity may increase up to 1870 MMcf/d

April 30

2150

Tionesta Station Maintenance

March Max Capacity: 2270
April Max Capacity: 2240

Baja Path Maintenance

Capacity in MMcf/d
Dates Kettleman Hinkley Topock Maintenance Notes

March 24 - 28

830

780

975

Hinkley Station Maintenance

L300A Pipeline Maintenance 

March 29 - 31

830

840

975

Hinkley Station Maintenance

L300A Pipeline Maintenance 

April 01 - 13

550

600

975

L300A Pipeline Maintenance 

Hinkley Station Maintenance

April 14

550

500

975

L300A Pipeline Maintenance 

Hinkley Station Maintenance

April 15 - 18

510

500

975

Milpitas Station Maintenance 

Hinkley Station Maintenance

April 19 - 29

510

840

975

Milpitas Station Maintenance 

Hinkley Station Maintenance

April 30

510

840

930

Milpitas Station Maintenance 

Hinkley Station Maintenance

Topock Station Maintenance

March Max Capacity: 975
April Max Capacity: 975

Limitations at Specific Interconnect Points

Redwood Path

Dates Capacity Maintenance Notes

March 25 - 27

0

Wild Goose Storage Facility Net Withdrawal

March 25 - 27

0

Central Valley Storage Facility Net Withdrawal

April 01 - 09

41

Wild Goose Storage Facility Net Withdrawal

April 01 - 09

13

Central Valley Storage Facility Net Withdrawal

April 22 - 28

101

Wild Goose Storage Facility Net Withdrawal

April 22 - 28

32

Central Valley Storage Facility Net Withdrawal

April 29

23

Wild Goose Storage Facility Net Withdrawal

April 29

7

Central Valley Storage Facility Net Withdrawal

Capacity information is in MMcf/d

Baja Path

Dates Capacity Maintenance Notes

March 01 - 31

797

El Paso Interconnect at Topock limited for maintenance

April 01 - 30

774

El Paso Interconnect at Topock limited for maintenance

Capacity information is in MMcf/d

Storage Maintenance

Injection

Dates Capacity Maintenance Notes

Capacity information is in MMcf/d

Withdrawal

Dates Capacity Maintenance Notes

Capacity information is in MMcf/d

Pipeline Maintenance History Download

Maintenance will not appear in the archive until after it's been removed from the Operating Data | Pipeline Maintenance page above. You can download Redwood and Baja pipeline maintenance information as far back as November 1, 2016. You can download Limitations at Specific Interconnect Point information as far back as March 21, 2018. You can download Storage Maintenance information as far back as December 11, 2020.

Prospective Maintenance Document

Last revised: March 20, 2025

Download our Prospective Maintenance document for a 6-12 month outlook of proposed maintenance on the CGT pipeline system. Note that this document is revised monthly and is offered in addition to our existing month-out Pipeline Maintenance information listed above.

 

Report any accessibility barriers you encounter when using our site by contacting CGTPipeRanger@pge.com. The mailbox is monitored during our business hours (M-F; 6am-3pm PT).  We will respond within 3 business days.